How Long Will Your Renovation Take?
One of the most common questions we get at Build My Home Ltd is "how long will my renovation take?" Here's a realistic guide based on our experience completing hundreds of projects in Brantford, Kitchener, and the surrounding area.
Typical Renovation Timelines
- Bathroom Renovation: 2–4 weeks (simple refresh: 1–2 weeks)
- Kitchen Renovation: 3–8 weeks (depending on layout changes)
- Basement Finishing: 4–8 weeks
- Legal Basement Suite: 8–14 weeks (including permits)
- Full Home Renovation: 3–6 months
- Room Addition: 2–4 months
- Deck / Patio: 1–3 weeks
The Renovation Process: Phase by Phase
Phase 1: Planning & Design (1–4 weeks). This includes initial consultation, measurements, design decisions, material selection, and getting your quote finalized.
Phase 2: Permits (2–4 weeks). If your project requires a building permit, allow 2–4 weeks for application and approval. Your contractor should handle this.
Phase 3: Demolition & Rough-Ins (1–3 weeks). Tear-out of existing materials, followed by framing, plumbing rough-in, electrical rough-in, and HVAC work. Inspections happen at this stage.
Phase 4: Insulation & Drywall (1–2 weeks). Insulation installation, vapour barrier, drywall hanging, taping, mudding, and sanding. Another inspection may be required.
Phase 5: Finishes (2–4 weeks). This is where your renovation comes to life: flooring, cabinets, countertops, tile, painting, trim, fixtures, and appliances.
Phase 6: Final Touches & Inspection (3–5 days). Final details, touch-up paint, hardware installation, cleaning, and the final building inspection.
Common Causes of Delays
- Permit delays: Municipal backlogs can add weeks
- Material delays: Custom orders or back-ordered items
- Hidden issues: Mould, asbestos, structural problems discovered during demolition
- Change orders: Changing your mind mid-project adds time and cost
- Weather: For projects involving exterior work
How to Keep Your Project on Track
Make all design decisions before construction starts. Finalize material selections early. Avoid changes mid-project. Maintain clear communication with your contractor. Have a 10-15% contingency budget for unexpected issues.